Loading...
 
 

Coronavirus and Force Majeure

Published: 18 Feb 2020 Average Rating: unrated Print
 

Author: Tim Cummins

At the time of the Global Financial Crisis, the Force Majeure clause briefly rose to second place in the annual study of the most negotiated terms. Those buyers and suppliers who had sufficient power to drive changes sought to reshape the clause in ways that would work to their advantage.

Now, the outbreak of the Coronavirus and its fast-emerging impact on world trade has once again elevated the importance of Force Majeure clauses and many are asking how it will impact obligations of contract performance.

Finding the contract

It is at times like this that many organizations wish that they had better control and insight into their contracts. In order to establish the likely impact of this health emergency, they firstly need to be able to find their contracts and secondly they need to analyze what they say. A fortunate few will have robust and searchable repositories and have also deployed the sort of AI or NLP tools that support rapid analysis and review of the relevant terms.

But beyond this, is the nature of the emergency now declared by the World Health Organization likely to qualify as a Force Majeure event? In order to qualify as a public health emergency, it must (i) be extraordinary; (ii) constitute a public health risk to other States through the international spread of disease; and (iii) potentially require a coordinated international response. These factors clearly indicate the seriousness of the event, but in themselves do not of course generate the basis for a claim of Force Majeure.

Determination of applicability will always depend on the specifics of the clause and how it is written. But there are other factors to be taken into account in any adjudication relating to the applicability of Force Majeure. Among the critical factors are likely to be industry custom, whether or not the event in question was unforeseeable, and whether adequate efforts have been made to mitigate the consequences.

Further considerations  

Thoughts on this topic do not simply end with the question of whether Force Majeure applies (and in many cases, I suspect it will). There are also factors such as termination rights to be considered, This will most likely depend on the duration of the event – so right now, not something we can forecast.

There are also likely to be related terms to consider. For example, if Force Majeure applies, what consequence does it have on things such as an extension of time, or future obligations on supply, or possible recovery of additional costs. Also, are losses in any way recoverable under insurance?

Finally, what about a situation where there is no Force Majeure clause – does this mean an obligation to perform? the answer is not necessarily, because the concept of 'frustration' may apply.

The content of this blog should not be considered legal advice.

 
 
 

Related Discussions

Please sign in or register to post on this forum

ABB Enterprise Software
2020-02-27 23:57:03

Corona Virus

If anyone has encountered the same discussion - any ideas how to qualify and cover corona-virus and such nature of potential disruptions in the contract? What approxim...
 
 
 
Replies: 2

erdemir engineering management and co...
2020-02-09 09:11:49

Force Majeure due to Coronavirus

Can coronavirus considered as a force majeure in contract management ?
 
 
 
 
 
 
 
Replies: 6

N.M.I.A.L.
2019-11-14 15:27:49

Warranty & Discontinuation of Product

Hi everybody, Now we have a situation here in terms of warranty and product discontinuation : A large facility was being constructed which required ~1500 architectu...
 
 
 
 
Replies: 3

ATCO Electric
2019-09-10 14:54:12

Acceleration Claims Vs Delay Backcharges

Did someone face a situation for a construction contract, when contract has submitted claims for delays from Owner and acceleration efforts, and on the other hand Owne...
 
 
 
Replies: 2
Anonymous
2019-01-03 10:38:17

ADVICE NEEDED: difficult contract management position - customer & shareholder contracts

Hi, My company outsources key services to another company (Company X). However, we also own a portion of Company X as it was set up as a joint venture. I am the contr...
 
 
 
 
 
Replies: 4
Anonymous
2018-08-09 19:51:57

Bankrupt Customer; Principles Formed a New Company

Happy Thursday Everyone! Hope you are all doing well. Hoping to receive some guidance and speaking points on a request I recieved from my sales folks. We complete...
 
 
 
Replies: 2

CGCL
2018-05-15 13:47:24

Terminating a Contract

We have a contractor for a service and we are looking to part ways with the vendor. The contractor has emailed us and said they are no longer interested in performing ...
 
 
 
 
 
 
 
 
 
Older entries »
Replies: 8